Envocare Maintenance were contracted direct by Office Depot to improve the natural daylight in their Crawley Depot and stop the constant water that was penetrating through the old big six rooflights and sheets.

This project came with logistical and health and safety problems with the roof being an old original Asbestos roof.

We had to work around a live working depot inside and take down the lights along with spanning across fragile sheets to install the new lights.

This project has not only improved the light within the building but also ensured that any leaks that were evident have now been eradicated meaning that the building life expectancy has now been increased.